Project Description: |
GREAT BARRINGTON- CULVERT REPLACEMENT, ROUTE 23 OVER HUBBARD BROOK
The purpose of this project is to completely replace the culvert and reconstruct the approach roadways.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Construction Begins: | Winter 2050/2051 |
Project Manager: | Ryan P. Wilcox |
Estimated Total Contract Cost: | $3,151,000.00 |
Estimated Total Federal Participating Construction Cost: | $3,439,420.00 |
District: | District 1 |
Current Status: | The Contract Scope of Work has been sent to the Design Engineer for consideration (as of 06/03/2024 ) |
|
Bridges |
|
|
|