Project Description:
FRAMINGHAM- BIKE PATH CONSTRUCTION OF BRUCE FREEMAN RAIL TRAIL, FROM EATON ROAD WEST TO FROST STREET
The project will consist of Phase 1 of the final phase of the Bruce Freeman Rail Trail that once complete will provide connectivity from Lowell to Framingham. Phase 1 proposes approximately 1.6 miles of shared use path with potential for boardwalk structures over critical environmental resource areas (assumed 500 LF). The trail corridor will intersect at grade with 2 roadways and crossing treatments will be evaluated.
Location:
  • Town of Framingham
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Summer 2029
    Project Manager: David Shedd
    Estimated Total Contract Cost: $7,222,500.00
    Estimated Total Federal Participating Construction Cost: $7,490,000.00
    Funding Provision: This project is planned to be funded through the 2029 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2029
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: FRAMINGHAM
    Category: Advertised Projects Constr.
    Budget Section: 2C
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Congestion Mitigation/Air Quality (CMAQ)
    Federal Cost: $6,950,720.00
    State Cost: $1,737,680.00
    Total Cost: $8,688,400.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/22/2023
    Project Need Form PNF Approved 11/09/2023
    Project Initiation Form PIF Entered 11/22/2023
    Project Initiation Form PIF Approved 11/20/2023
    Project Initiation Form PRC Submitted 11/22/2023
    Project Review Committee PRC Approved 12/14/2023
    Project Management