DISTRICT 3- ACCESSIBILITY IMPROVEMENTS AT MULTIPLE LOCATIONS (NORTHERN PROJECT)
The first location is in Townsend at the intersection of Route 119 Main St at W Elm St and Canal St. Two deficient pedestrian curb ramps at the intersection will be reconstructed and upgraded to full ADA compliance. An additional six curb ramps are recommended to be constructed at this location with corresponding painted crosswalks. It is also recommended that an additional 600 feet of sidewalk be constructed on the north side of the road and 100 feet of sidewalk on the south side of the road. Lastly, curb line adjustments should be evaluated to minimize utility and ROW impacts. The second location is in Lunenburg along Route 2A Massachusetts Ave in the vicinity of Tilton Ave where two deficient pedestrian curb ramps will be reconstructed and upgraded to full ADA compliance. An additional two curb ramps are recommended to be constructed at this location with corresponding painted crosswalks. It is also recommended that sidewalk be constructed totaling 550 feet on the north side of the road and 550 feet on the south side of the road. A 100 foot landscape wall may be needed to retain soil and allow for the sidewalk construction. Additionally an RRFB should be evaluated for the crosswalk across Route 2A. The third location is in Westminster along Route 2A Main St in the vicinity of Adams St and Church St where all deficient pedestrian curb ramps will be reconstructed and upgraded to full ADA compliance. It is recommended that an additional 75 feet of sidewalk be added on the south side of E Main St. Additionally an Rapid Rectangular Flashing Beacon should be evaluated for the crosswalk across Route 2A.
Location:
Design Responsibility: Consultant
Right of Way Responsibility: MassDOT
Construction Begins: Summer 2030
Project Manager: Dongke Yu
Estimated Total Contract Cost: $1,618,200.00
Estimated Total Federal Participating Construction Cost: $1,756,994.00
Funding Provision: This project is planned to be funded through the 2030 Transportation Improvement Program for the STATEWIDE.
District: District 3
Current Status: This project is in the preliminary design phase.

Contracts (1) Progress
# 115769 -- Design -- Services
Statewide - Master Service Agreement for design and review services. Final

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2030
    Responsible MPO: STATEWIDE
    Location: District
    Districts: District 3
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $1,574,266.40
    State Cost: $393,566.60
    Total Cost: $1,967,833.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/29/2023
    Project Need Form PNF Approved 11/29/2023
    Project Initiation Form PIF Entered 11/29/2023
    Project Initiation Form PIF Approved 11/29/2023
    Project Initiation Form PRC Submitted 12/01/2023
    Project Review Committee PRC Approved 12/14/2023