Project Description:
SANDISFIELD- RESURFACING AND RELATED WORK ON ROUTE 8
The purpose of this project is to resurface travel-lanes and shoulders on State Highway Route 8 and replace signage and guardrail as needed.
Location:
  • Town of Sandisfield
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $5,566,506.17
    Estimated Total Federal Participating Construction Cost: $5,703,361.91
    District: District 1
    Current Status: 100% Package Received (as of 08/12/2024 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/05/2024
    Project Need Form PNF Approved 01/05/2024
    Project Initiation Form PIF Entered 01/05/2024
    Project Initiation Form PIF Approved 01/05/2024
    Project Initiation Form PRC Submitted 01/24/2024
    Project Review Committee PRC Approved 01/23/2024
    Project Management
    100% Design 100% Package Received 08/12/2024
    25% Design 25% Package Received 06/05/2024
    75% Design 75% Package Received 06/05/2024
    75% Design 75% Package Comments to DE 07/15/2024
    Final Design PS&E Received 08/12/2024