Project Description:
DISTRICT 5- SCHEDULED AND EMERGENCY TREE TRIMMING, REMOVAL, AND SIGHT DISTANCE CLEARING VARIOUS LOCATIONS AREA D
Work will involve the removal of hazardous trees/limbs and removal of vegetation to establish clear zones and expose signage.
Location:
Construction Begins: Summer 2024
Resident Engineer: Gabriel Rodrigues
Construction Bid Price: $1,241,320.00
District: District 5
Current Status: Contractor is available for emergency storm response. Priority List in progress, storm cleanup in progress Cape-wide. Scheduled work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 04/30/2026)

Contracts (1) Progress
# 126173 -- Construction Contract
Scheduled And Emergency Tree Trimming, Removal, and Sight Distance Clearing Various Locations Area D 73% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/25/2024
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Contractor is available for emergency storm response. Priority List in progress, storm cleanup in progress Cape-wide. Scheduled work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/18/2024
    Project Need Form PNF Approved 01/18/2024
    Project Initiation Form PIF Entered 01/18/2024
    Project Initiation Form PIF Approved 01/18/2024
    Project Initiation Form PRC Submitted 01/23/2024
    Project Review Committee PRC Approved 01/24/2024
    Project Status Advertised 06/01/2024
    Project Management
    100% Design 100% Package Received 03/19/2024
    Final Design PS&E Received 03/19/2024
    Final Design PS&E to FAPRO 05/01/2024