Project Description:
DISTRICT 5- SCHEDULED AND EMERGENCY TREE TRIMMING, REMOVAL, AND SIGHT DISTANCE CLEARING AREAS A, B, & C
Work involves the removal of hazardous trees/limbs and related vegetation to imprve sight distance, remove hazards, expose signage, and establish clear zones.
Location:
Design Responsibility: In-House Boston
Right of Way Responsibility: MassDOT
Project Manager: Andre Breneville
Estimated Total Contract Cost: $1,800,000.00
Estimated Total Federal Participating Construction Cost: N/A
District: District 5
Current Status: Final Package to FAPRO (as of 05/01/2024 )

Contracts (0) Progress
No contracts associated with this project

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/18/2024
    Project Need Form PNF Approved 01/18/2024
    Project Initiation Form PIF Entered 01/18/2024
    Project Initiation Form PIF Approved 01/18/2024
    Project Initiation Form PRC Submitted 01/23/2024
    Project Review Committee PRC Approved 01/24/2024
    Project Management
    100% Design 100% Package Received 03/19/2024
    Final Design PS&E Received 03/19/2024
    Final Design PS&E to FAPRO 05/01/2024