Project Description:
DISTRICT 6- SCHEDULED & EMERGENCY VEGETATION MANAGEMENT (MECHANICAL) AT VARIOUS LOCATIONS
Location:
Design Responsibility: In-House Boston
Right of Way Responsibility: MassDOT
Construction Begins: Summer 2024
Project Manager: Andre Breneville
Estimated Total Contract Cost: $2,050,000.00
Estimated Total Federal Participating Construction Cost: N/A
District: District 6
Current Status: This project has been advertised for construction bids. (as of 03/30/2024 )

Contracts (0) Progress
No contracts associated with this project

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/21/2024
    Project Need Form PNF Approved 02/21/2024
    Project Initiation Form PIF Entered 02/21/2024
    Project Initiation Form PIF Approved 02/21/2024
    Project Initiation Form PRC Submitted 02/21/2024
    Project Review Committee PRC Approved 02/28/2024
    Project Status Advertised 03/30/2024
    Project Management
    100% Design 100% Package Received 03/01/2024
    Final Design PS&E Received 03/05/2024
    Final Design PS&E to FAPRO 03/12/2024