Project Description:
CAMBRIDGE- NEIGHBORHOOD ELECTRIC VEHICLE CHARGING INFRASTRUCTURE (MA287)
This project would construct multiple electric vehicle charging stations in Cambridge neighborhoods.
Location:
  • City of Cambridge
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2026/2027
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $1,417,366.87
    Estimated Total Federal Participating Construction Cost: $1,530,916.54
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 09/12/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/28/2024
    Project Need Form PNF Approved 03/28/2024
    Project Initiation Form PIF Entered 03/28/2024
    Project Initiation Form PIF Approved 03/28/2024
    Project Initiation Form PRC Submitted 03/28/2024
    Project Review Committee PRC Approved 05/31/2024
    Project Status Advertised 09/12/2026
    Project Management
    100% Design 100% Package Received 05/08/2026
    100% Design 100% Package Comments to DE 06/09/2026
    25% Design 25% Package Received 01/26/2026
    75% Design 75% Package Received 05/08/2026
    Final Design PS&E Received 08/03/2026
    Final Design PS&E to FAPRO 08/31/2026