Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CAMBRIDGE- NEIGHBORHOOD ELECTRIC VEHICLE CHARGING INFRASTRUCTURE (MA287)
This project would construct multiple electric vehicle charging stations in Cambridge neighborhoods.
Location:
  • City of Cambridge
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2025/2026
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $1,145,833.34
    Estimated Total Federal Participating Construction Cost: $1,250,000.00
    Funding Provision: This project is planned to be funded through the 2025 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2025
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: CAMBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • Demo ID MA 287. Federal earmark rec'd in 2023 Appropriations Act. Deadline for obligation is 9/30/2026. Programmed in STIP as S12992
  • Category FA - High Priority Projects (HPP)
    Federal Cost: $1,000,000.00
    State Cost: $250,000.00
    Total Cost: $1,250,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/28/2024
    Project Need Form PNF Approved 03/28/2024
    Project Initiation Form PIF Entered 03/28/2024
    Project Initiation Form PIF Approved 03/28/2024
    Project Initiation Form PRC Submitted 03/28/2024
    Project Review Committee PRC Approved 05/31/2024
    Project Management