Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CAMBRIDGE- NEIGHBORHOOD ELECTRIC VEHICLE CHARGING INFRASTRUCTURE (MA287)
This project would construct multiple electric vehicle charging stations in Cambridge neighborhoods.
Location:
  • City of Cambridge
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Construction Begins: Winter 2026/2027
    Project Manager: Koby J Lemrise
    Estimated Total Contract Cost: $1,417,366.87
    Estimated Total Federal Participating Construction Cost: $1,530,916.54
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 09/12/2026 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: CAMBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

  • Formerly programmed as S13381; Project ID revised via administrative modification. $1.25M earmark (MA 287).
  • Category FA - High Priority Projects (HPP)
    Federal Cost: $952,869.60
    State Cost: $238,217.40
    Total Cost: $1,191,087.00

    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: CAMBRIDGE
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

  • added $300k STBG via STIP action 11
  • Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $240,000.00
    State Cost: $60,000.00
    Total Cost: $300,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 03/28/2024
    Project Need Form PNF Approved 03/28/2024
    Project Initiation Form PIF Entered 03/28/2024
    Project Initiation Form PIF Approved 03/28/2024
    Project Initiation Form PRC Submitted 03/28/2024
    Project Review Committee PRC Approved 05/31/2024
    Project Status Advertised 09/12/2026
    Project Management
    100% Design 100% Package Received 05/08/2026
    100% Design 100% Package Comments to DE 06/09/2026
    25% Design 25% Package Received 01/26/2026
    75% Design 75% Package Received 05/08/2026
    Final Design PS&E Received 08/03/2026
    Final Design PS&E to FAPRO 08/31/2026