Project Description:
DUDLEY- CULVERT REPLACEMENT ON ROUTE 131 (BETWEEN MM 7.2 AND MM 7.4)
The project aims to replace an undersized culvert to meet stream crossing standards to the maximum extent practicable. According to StreamStats, the tributary to the Quinebaug River is 7.5 feet. The existing culvert is only 36 inches.
Location:
  • Town of Dudley
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Joseph Gyujong Yoo
    Estimated Total Contract Cost: $2,107,500.00
    Estimated Total Federal Participating Construction Cost: $2,276,025.00
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/03/2024
    Project Need Form PNF Approved 03/25/2024
    Project Initiation Form PIF Entered 04/03/2024
    Project Initiation Form PIF Approved 04/02/2024
    Project Initiation Form PRC Submitted 04/04/2024
    Project Review Committee PRC Approved 05/31/2024
    Project Management