Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
LOWELL- CONCRETE PAVEMENT REHABILITATION ON ROUTE 133
This project consists of concrete pavement restoration on Route 133 in Lowell through several methods including, but not limited to, full and partial depth concrete repairs, cleaning and resealing existing joints, crack sealing, joint and surface spall repair, and diamond grinding. Additional incidental work includes adjusting and repairing existing drainage structures that are within concrete pavement repair locations, installing new pavement markings to match existing, and temporary traffic management during construction.
Location:
  • City of Lowell
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Cody Holemo
    Estimated Total Contract Cost: $3,581,250.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/24/2024
    Project Need Form PNF Approved 04/24/2024
    Project Initiation Form PIF Entered 04/24/2024
    Project Initiation Form PIF Approved 04/24/2024
    Project Initiation Form PRC Submitted 04/24/2024
    Project Review Committee PRC Approved 05/31/2024
    Project Management