Project Description:
DISTRICT 5- ACCESSIBILITY IMPROVEMENTS AT MULTIPLE LOCATIONS (NORTHERN PROJECT)
The purpose of this project is to reconstruct and upgrade all deficient pedestrian curb ramps to full ADA compliance at four locations. The first location is in Brockton at the intersection of Route 27 (North Pearl St) & Oak St Ext. The second location is in Brockton at the intersection of North Pearl Street & Route 27. The third location is in Brockton along North Pearl Street between Healey Terrace and Cashman Rd. The fourth location is in Hingham along Whiting St (Route 53) from Peter Hobart Drive to Accord Ln. Additional curb ramps, sidewalk, crossings and crossing enhancements, curb extensions, and pedestrian signal upgrades will be evaluated on a location by location basis.
Location:
Design Responsibility: Consultant
Right of Way Responsibility: MassDOT
Construction Begins: Summer 2031
Project Manager: Yaseen Al Abdullah
Estimated Total Contract Cost: $1,904,175.00
Estimated Total Federal Participating Construction Cost: $2,067,497.25
Funding Provision: This project is planned to be funded through the 2030 Transportation Improvement Program for the STATEWIDE.
District: District 5
Current Status: The Notice to Proceed to begin work on the contract has been issued (as of 03/16/2026 )

Contracts (1) Progress
# 115784 -- Design -- Services
Statewide - Master Service Agreement for design and review services. Final

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2030
    Responsible MPO: STATEWIDE
    Location: District
    Districts: District 5
    Category: Advertised Projects Constr.
    Budget Section: 2B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Surface Trans. Block Grant (STBG)
    Federal Cost: $1,918,637.60
    State Cost: $479,659.40
    Total Cost: $2,398,297.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/25/2024
    Project Need Form PNF Approved 04/25/2024
    Project Initiation Form PIF Entered 04/25/2024
    Project Initiation Form PIF Approved 04/25/2024
    Project Initiation Form PRC Submitted 04/26/2024
    Project Review Committee PRC Approved 05/31/2024
    Project Management
    Consultant Contract Process NTP Issued 03/16/2026