Project Description: |
BRAINTREE- RECONSTRUCTION OF ALLEN STREET (MA285)
This project will reconstruct Allen Street in Braintree, converting the two-way to a one-way and providing a new shared use path.
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Municipality |
Construction Begins: | Winter 2025/2026 |
Project Manager: | Yaseen Al Abdullah |
Estimated Total Contract Cost: | $6,257,594.60 |
Estimated Total Federal Participating Construction Cost: | $3,149,999.30 |
District: | District 6 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|