| Project Description: |
NEWTON- BRIDGE PRESERVATION, N-12-059 (2FM), I-95/ST128 OVER QUINOBEQUIN ROAD
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Construction Begins: | Autumn 2027 |
| Project Manager: | Alina Daragan![]() |
| Estimated Total Contract Cost: | $6,704,462.08 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 6 |
| Current Status: | 25% Package Comments to DE (as of 10/09/2026 ) |
|