Project Description:
DISTRICT 5- SCHEDULED AND EMERGENCY BRIDGE DECK AND JOINT REPAIRS AT VARIOUS LOCATIONS
SCHEDULED & EMERGENCY BRIDGE DECK AND JOINT REPAIRS PERFORMED ON BRIDGES IN DISTRICT 5
Location:
Construction Begins: Winter 2024/2025
Resident Engineer: Scott Borges
Construction Bid Price: $2,140,805.00
District: District 5
Current Status: Foxborough – WO #1 - Joint replacement at Bridge F-06-022 (3QX) I-95 SB over Oak Street.?? To be scheduled. Canceled due to Xfinity and Gilette event schedule. To be scheduled. Mansfield - WO #2 - Perform pothole, wearing surface and joint header repairs at Bridge M-03-034 (3RH) I-495 SB over Forbes/Amtrak/MBTA.? WO estimate approved. To be scheduled. Taunton - WO #3 – Install traffic markings at Bridge T-01-059 (3RV, 3RW) I-495 SB & NB over Snake River.? Night Operations. Work scheduled for 6/15/25 - Cancelled due to unfilled police details. Schedule TBD. N. Attleborough – WO #7 - reinforced concrete deck repairs at Bridge N-16-047 (3VJ) ST.152 Toner Blvd over I-95. To be scheduled. Norwood – WO #8 - Concrete deck repairs and placement of new joints at Bridge N-25-032 (40M) Canton Street over RR CSX Spur QBL 2.18. To be scheduled. Norton – Priority WO's #12 & 13 - Reinforced concrete deck repairs at Bridge N-23-035 (3RL) & (3RM) I-495 NB & SB over Canoe River. WO #12 I-495 NB completed on 11/12/25. WO #13 to be scheduled pending temps. Mansfield – Priority WO #14 - Wearing surface/pothole and joint header repair at Bridge M-03-032 (3RF) I-495 NB over Rumford River. To be scheduled. Raynham – Priority WO #18 - Pothole and joint header repair at Bridge R-02-027 (3T2) I-495 SB over MBTA. To be scheduled. Dennis – Priority WO's #21 & 22 - Joint Installation at Bridge D-07-010 (46P) & D-07-012 (46N) US.6 WB & EB over Bass River. To be scheduled following MDOT Maintenance resurfacing. Resurfacing complete. Awating warmer temps. (as of 04/15/2026)
Additional Info: Dennis – Priority WO's #21 & 22 - Joint Installations at Bridges D-07-010 (46P) US.6 WB & D-07-012 (46N) US.6 EB over Bass River. To be scheduled following MDOT Maintenance resurfacing. Schedule TBD. Sharon – Priority WO #24 - Joint Installation at Bridge S-09-004 (ACY) ST.27 Depot Street over Amtrak/MBTA. Work being coordinated with Town Engineer. Joints to be prepped temporarily before mill and pave early May (by others). Schedule TBD. Dennis – Yarmouth – Priority WO #28 - Reinforced Concrete Deck Excavation and Placement of Repair Concrete at Bridge D-07-004 (47T) ST.28 Main Street over Bass River. Scheduled for 4/16/26 & 4/17/26 (Day). One lane in each direction to be maintined. Fall River – Priority WO #29 - Wearing surface and reinforced concrete deck repairs at Bridge F-02-068 (3TM) I-195 over Quequechan Street in Fall River. Work started 4/12/26 (night) - on-going. New Bedford – Priority WO #30 - Reinforced concrete deck repairs at Bridge N-06-031 (3Y1) Hillman St. over ST.18 & Ramp A in New Bedford. To be scheduled. Scheduled work hours are 9pm through 5am (as of 04/15/2026)

Contracts (1) Progress
# 128614 -- Construction Contract
Scheduled and Emergency Bridge Deck and Joint Repairs at Various Locations 25% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/09/2025
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Foxborough – WO #1 - Joint replacement at Bridge F-06-022 (3QX) I-95 SB over Oak Street.?? To be scheduled. Canceled due to Xfinity and Gilette event schedule. To be scheduled. Mansfield - WO #2 - Perform pothole, wearing surface and joint header repairs at Bridge M-03-034 (3RH) I-495 SB over Forbes/Amtrak/MBTA.? WO estimate approved. To be scheduled. Taunton - WO #3 – Install traffic markings at Bridge T-01-059 (3RV, 3RW) I-495 SB & NB over Snake River.? Night Operations. Work scheduled for 6/15/25 - Cancelled due to unfilled police details. Schedule TBD. N. Attleborough – WO #7 - reinforced concrete deck repairs at Bridge N-16-047 (3VJ) ST.152 Toner Blvd over I-95. To be scheduled. Norwood – WO #8 - Concrete deck repairs and placement of new joints at Bridge N-25-032 (40M) Canton Street over RR CSX Spur QBL 2.18. To be scheduled. Norton – Priority WO's #12 & 13 - Reinforced concrete deck repairs at Bridge N-23-035 (3RL) & (3RM) I-495 NB & SB over Canoe River. WO #12 I-495 NB completed on 11/12/25. WO #13 to be scheduled pending temps. Mansfield – Priority WO #14 - Wearing surface/pothole and joint header repair at Bridge M-03-032 (3RF) I-495 NB over Rumford River. To be scheduled. Raynham – Priority WO #18 - Pothole and joint header repair at Bridge R-02-027 (3T2) I-495 SB over MBTA. To be scheduled. Dennis – Priority WO's #21 & 22 - Joint Installation at Bridge D-07-010 (46P) & D-07-012 (46N) US.6 WB & EB over Bass River. To be scheduled following MDOT Maintenance resurfacing. Resurfacing complete. Awating warmer temps.
    Additional Info
    Dennis – Priority WO's #21 & 22 - Joint Installations at Bridges D-07-010 (46P) US.6 WB & D-07-012 (46N) US.6 EB over Bass River. To be scheduled following MDOT Maintenance resurfacing. Schedule TBD. Sharon – Priority WO #24 - Joint Installation at Bridge S-09-004 (ACY) ST.27 Depot Street over Amtrak/MBTA. Work being coordinated with Town Engineer. Joints to be prepped temporarily before mill and pave early May (by others). Schedule TBD. Dennis – Yarmouth – Priority WO #28 - Reinforced Concrete Deck Excavation and Placement of Repair Concrete at Bridge D-07-004 (47T) ST.28 Main Street over Bass River. Scheduled for 4/16/26 & 4/17/26 (Day). One lane in each direction to be maintined. Fall River – Priority WO #29 - Wearing surface and reinforced concrete deck repairs at Bridge F-02-068 (3TM) I-195 over Quequechan Street in Fall River. Work started 4/12/26 (night) - on-going. New Bedford – Priority WO #30 - Reinforced concrete deck repairs at Bridge N-06-031 (3Y1) Hillman St. over ST.18 & Ramp A in New Bedford. To be scheduled. Scheduled work hours are 9pm through 5am
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/30/2024
    Project Initiation Form PIF Entered 05/30/2024
    Project Initiation Form PRC Submitted 05/30/2024
    Project Review Committee PRC Approved 06/03/2024
    Project Status Advertised 11/02/2024
    Project Management
    100% Design 100% Package Received 08/22/2024
    100% Design 100% Package Comments to DE 09/12/2024
    75% Design 75% Package Received 07/03/2024
    75% Design 75% Package Comments to DE 08/08/2024
    Final Design PS&E Received 09/23/2024
    Final Design PS&E to FAPRO 10/28/2024