Project Description:
DISTRICT 5- DRAWBRIDGE OPERATION, REPAIR AND SYSTEMATIC PRESERVATION AT VARIOUS LOCATIONS (INCLUDING MARTHA'S VINEYARD)
ALL MOVABLE BRIDGES UNDER THE CONTROL OF DISTRIC 5 AND PUMP HOUSE LOCATED AT COPELAND DRIVE IN MANSFIELD
Location:
Construction Begins: Winter 2024/2025
Resident Engineer: Louis daPonte
Construction Bid Price: $5,620,255.00
District: District 5

Contracts (1) Progress
# 129072 -- Construction Contract
Drawbridge Operation, Repair and Systematic Preservation at Various Locations (Including Martha's Vineyard) 57% Complete

Bridges

Contract Dates
Notice to Proceed: 03/18/2025
Contract Information
Project Designer: In-House Boston
Funding Source: Non Federal Aid
See the Milestone Details tab for additional Project information
Initiation
no comments
Scoping
no comments
Property Impacts - Right of Way
no comments
Environmental Impacts
no comments
Project Design
no comments
Project Funding
no comments
Public Involvement
no comments
Construction
no comments
Accelerated Bridge Program
no comments
No TIP Data Available For This Project
Project Task Information
Project Status
Project Need Form PNF Entered 05/30/2024
Project Initiation Form PIF Entered 05/30/2024
Project Initiation Form PRC Submitted 05/30/2024
Project Review Committee PRC Approved 06/03/2024
Project Status Advertised 12/28/2024
Project Management
100% Design 100% Package Received 11/13/2024
100% Design 100% Package Comments to DE 12/02/2024
75% Design 75% Package Received 08/30/2024
75% Design 75% Package Comments to DE 10/29/2024
Final Design PS&E Received 12/09/2024
Final Design PS&E to FAPRO 12/19/2024