| Project Description: |
TAUNTON- BRIDGE PRESERVATION, T-01-058 (3YF), BAY STREET OVER INTERSTATE 495
PERFORM EXCAVATION OF EXISITING WEARING SURFACE AND REPLACE WITH 5" LMC OVERLAY, CLEARING AND THINNING, AND STEEL REPAIRS AS NEEDED
|
| Location: |
|
| Construction Begins: | Autumn 2025 |
| Resident Engineer: | Matthew Blackwell![]() |
| Construction Bid Price: | $4,577,477.50 |
| District: | District 5 |
| Current Status: | The contractor poured the extended deck ends. He plans to form the new safety curbs and pour them next week. The crew will then begin installing the bidwell screed to prepare for the new concrete overlayment. The bridge painting contractor is currently installing the temporary shielding for the basting containment under the bridge. Scheduled work hours are 6am through 4pm (as of 08/03/2026) |
|