WORCESTER- BRIDGE PRESERVATION, W-44-099 (214), MILLBROOK STREET OVER I-190 (SB) AND W-44-029 (23B) MILLBROOK STREET OVER RAILROAD
This contract includes the reconstruction of bridge joints, replacement of the existing bridge wearing surface, milling and repaving of the roadway and approaches, sidewalk repairs, addressing structural and safety concerns, and performing other related work. The project will include two (2) bridges located on Millbrook Street over the Railroad – Bridge No. W-44-029 (23B) and Millbrook Street over I-190 Southbound – Bridge No. W-44-099 (214) in Worcester. The work also includes setting up detours, coordinating, and implementing the Temporary Traffic Control Plan (TTCP) for each phase of work and milling of the pavement to a depth of 1 1/2” on the roadway between the bridges, the approaches, and extending to the limits specified in the drawings or as directed by the Engineer.
Location:
  • City of Worcester
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2025/2026
    Project Manager: Genesis Poz Diaz
    Estimated Total Contract Cost: $3,428,765.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: PS&E Received (as of 08/02/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/22/2024
    Project Initiation Form PIF Entered 06/22/2024
    Project Initiation Form PRC Submitted 06/22/2024
    Project Review Committee PRC Approved 06/25/2024
    Project Management
    100% Design 100% Package Received 06/25/2025
    100% Design 100% Package Comments to DE 07/16/2025
    75% Design 75% Package Received 04/23/2025
    75% Design 75% Package Comments to DE 06/13/2025
    Final Design PS&E Received 08/02/2025