Project Description:
TEMPLETON TO LANCASTER- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF ROUTE 2
This project is for the replacement and upgrading of guide and traffic signs on Route 2 from the Route 68 interchange in Templeton easterly to the Jackson Road interchange in Lancaster, including applicable signs on secondary roads intersecting Route 2
Location:
  • City of Fitchburg
  • City of Gardner
  • Town of Lancaster
  • City of Leominster
  • Town of Templeton
  • Town of Westminster
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2028
    Project Manager: Stephen Timmins
    Estimated Total Contract Cost: $2,691,000.00
    Estimated Total Federal Participating Construction Cost: $2,872,545.00
    Funding Provision: This project is planned to be funded through the 2028 Transportation Improvement Program for the Montachusett Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2028
    Responsible MPO: Montachusett Metropolitan Planning Organization
    Location: Municipality
    Cities: FITCHBURG
    GARDNER
    LANCASTER
    LEOMINSTER
    TEMPLETON
    WESTMINSTER
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $2,792,114.10
    State Cost: $310,234.90
    Total Cost: $3,102,349.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 07/02/2024
    Project Initiation Form PIF Entered 07/02/2024
    Project Initiation Form PRC Submitted 07/02/2024
    Project Review Committee PRC Approved 10/02/2024
    Project Management