Project Description: |
LEOMINSTER- BRIDGE REHABILITATION, L-08-004, MECHANIC STREET OVER MONOOSNOC BROOK
The proposed improvements include replacing/repairing beam that supports the downstream sidewalk; resurfacing bridge roadway; reconstructing one or both sidewalks; installing guardrail and fencing; and repairing retaining walls.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | Municipality |
Construction Begins: | Autumn 2025 |
Project Manager: | Ann Sullivan |
Estimated Total Contract Cost: | $1,180,001.00 |
Estimated Total Federal Participating Construction Cost: | $1,305,500.00 |
District: | District 3 |
Current Status: | This project is in the preliminary design phase. |
|