Project Description:
LEOMINSTER- CULVERT REPLACEMENT, L-08-053, AT PLEASANT STREET AND COLBURN STREET
The project consists of replacing the temporary 36” corrugated plastic pipe, installed as an emergency replacement of the previous 5’x 3’ box culvert that collapsed during the floods in September 2023. A 9’ x 4’ box culvert will be installed to replace the temporary culvert and meet the required hydraulic opening to the maximum extent practicable. Additionally, this project will include the restoration of the channel downstream of the culvert. The channel will be realigned and a flood storage area will be provided to mitigate flooding concerns to the condos further downstream. The channel will be armored on the eastern side to protect against the channel migrating and provide a buffer between the stream and the condos. Finally, approximately 500 feet downstream of the culvert, sediment deposits from the flood event in 2023 will be removed to restore the existing wetlands and reestablish a braided wetland system. Alongside the culvert and stream work, the project proposes improvements to the roadway, sidewalks, fencing, crosswalks, underground utilities, and drainage network that were impacted when the culvert failed in September 2023. Work will extend approximately 200 feet along Pleasant Street, 250 feet along Colburn Street, and 200 feet along Reservoir Brook downstream.
Location:
  • City of Leominster
  • Design Responsibility: Consultant
    Right of Way Responsibility: Municipality
    Project Manager: Greg Frazier
    Estimated Total Contract Cost: $3,129,197.50
    Estimated Total Federal Participating Construction Cost: $3,512,220.00
    District: District 3
    Current Status: 100% Package Received (as of 01/16/2026 )

    Contracts (1) Progress
    # 115795 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/22/2024
    Project Initiation Form PIF Entered 08/22/2024
    Project Initiation Form PRC Submitted 08/22/2024
    Project Review Committee PRC Approved 10/02/2024
    Project Management
    100% Design 100% Package Received 01/16/2026
    25% Design 25% Package Received 02/21/2025
    25% Design 25% Package Comments to DE 03/17/2025
    25% Design Design Public Hearing 04/01/2025
    75% Design 75% Package Received 01/16/2026