| Project Description: |
STURBRIDGE- IMPROVEMENTS ON ROUTE 20 (CHARLTON ROAD), FROM 1000 FEET EAST OF HALL ROAD TO EAST OF THE I-84 RAMPS
The proposed project would include safety improvements at the intersection of Hall Road including
possibly a roundabout and improve safe access to businesses along the corridor and provide safe
accommodations for pedestrians and bicyclists.
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Adam W Kiel![]() |
| Estimated Total Contract Cost: | $5,885,550.00 |
| Estimated Total Federal Participating Construction Cost: | $6,530,298.50 |
| District: | District 3 |
| Current Status: | The Notice to Proceed to begin work on the contract has been issued (as of 10/07/2025 ) |
|
Bridges |
||||||
|
|
|
|||||||||||||||||||||||