Project Description: |
WESTON- INTERSECTION IMPROVEMENTS AT ROUTE 20 AND HIGHLAND STREET
This project will reconstruct the intersection of Route 20 and Highland Avenue in Weston to improve safety.
|
Location: |
|
Design Responsibility: | Municipality |
Project Manager: | Douglas Johnson |
Estimated Total Contract Cost: | $6,241,500.00 |
Estimated Total Federal Participating Construction Cost: | $6,926,175.00 |
District: | District 6 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|