Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 4- ACCESSIBILITY IMPROVEMENTS AT MULTIPLE LOCATIONS (NORTHERN PROJECT)
The purpose of this project is to reconstruct and upgrade all deficient pedestrian curb ramps to full ADA compliance at five locations. Four of the locations are located in Salisbury along Route 1A (Beach Road). The first location is along Route 1A east of Glenwood Avenue and Sand Hill Road. The second location is at the intersection of Route 1A and Dock Lane. The third location is a midblock crossing located along Route 1A just east of Meaders Lane. The fourth location is another midblock crossing located along Route 1A west of Lynne Avenue. The fifth location in the project is in Haverhill, at the intersection of Route 97 (Broadway) and Carleton Street. Additional curb ramps, sidewalk, crossings and crossing enhancements, curb extensions, and pedestrian signal upgrades will be evaluated on a location by location basis.
Location:
  • City of Haverhill
  • Town of Salisbury
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $1,545,219.00
    Estimated Total Federal Participating Construction Cost: $1,676,386.53
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/30/2024
    Project Initiation Form PIF Entered 08/30/2024
    Project Initiation Form PRC Submitted 08/30/2024
    Project Review Committee PRC Approved 10/02/2024
    Project Management