Project Description: |
BOLTON- RECONSTRUCTION OF ROUTE 117 (MAIN STREET), FROM 200 FT WEST OF JOHN POWERS LANE TO THE INTERSECTION OF MECHANIC STREET INCLUDING CULVERT REPLACEMENT
The goal of this project is to replace a culvert, improve pedestrian facilities, provide bike accommodation, and improve intersection operations to serve existing volumes.
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Municipality |
Project Manager: | Douglas Johnson |
Estimated Total Contract Cost: | $6,992,500.00 |
Estimated Total Federal Participating Construction Cost: | $7,498,625.00 |
District: | District 3 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|