Project Description: |
PRINCETON- SUPERSTRUCTURE REPLACEMENT, P-16-008, OLD COLONY ROAD OVER WARE RIVER
|
Location: |
|
Right of Way Responsibility: | Municipality |
Project Manager: | Ryan P. Wilcox![]() |
Estimated Total Contract Cost: | $3,937,200.00 |
Estimated Total Federal Participating Construction Cost: | $4,393,741.50 |
District: | District 3 |
Current Status: | This project is in the preliminary design phase. |
|