Project Description:
BOSTON- BRIDGE DECK PRESERVATION OF B-16-259 AND B-16-260 ON I-93
This project targets the I-93 viaduct in Dorchester. The project will include repair/replacement of bridge joints, full replacement of the wearing surfaces, concrete deck patching, bridge barrier and railing repairs, and all traffic control required to complete the project.
Location:
  • City of Boston
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Winter 2025/2026
    Project Manager: Alina Daragan
    Estimated Total Contract Cost: $21,537,097.50
    Estimated Total Federal Participating Construction Cost: $22,234,985.75
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: PS&E Received (as of 08/01/2025 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $4,429,533.60
    State Cost: $1,107,383.40
    Total Cost: $5,536,917.00

    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $5,170,466.40
    State Cost: $1,292,616.60
    Total Cost: $6,463,083.00

    Planned Federal FY: 2028
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $7,200,000.00
    State Cost: $1,800,000.00
    Total Cost: $9,000,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/30/2024
    Project Initiation Form PIF Entered 10/30/2024
    Project Initiation Form PRC Submitted 10/30/2024
    Project Review Committee PRC Approved 11/22/2024
    Project Management
    100% Design 100% Package Received 06/25/2025
    100% Design 100% Package Comments to DE 07/16/2025
    100% Design 100% Package Comments to DE 07/16/2025
    75% Design 75% Package Received 05/05/2025
    75% Design 75% Package Comments to DE 06/04/2025
    Final Design PS&E Received 08/01/2025