Project Description:
BOSTON- BRIDGE DECK PRESERVATION OF B-16-259 AND B-16-260 ON I-93
This project targets the I-93 viaduct in Dorchester. The project will include repair/replacement of bridge joints, full replacement of the wearing surfaces, concrete deck patching, bridge barrier and railing repairs, and all traffic control required to complete the project.
Location:
  • City of Boston
  • Construction Begins: Winter 2025/2026
    Resident Engineer: Ammar A Alkhatatabih
    Construction Bid Price: $16,699,051.25
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6

    Contracts (1) Progress
    # 132904 -- Construction Contract
    Bridge Deck Preservation of B-16-259 and B-16-260 on I-93

    Bridges

    Contract Dates
    Notice to Proceed: 03/02/2026
    Contract Information
    Project Designer: In-House Boston
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $4,429,533.60
    State Cost: $1,107,383.40
    Total Cost: $5,536,917.00

    Planned Federal FY: 2027
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $5,170,466.40
    State Cost: $1,292,616.60
    Total Cost: $6,463,083.00

    Planned Federal FY: 2028
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BOSTON
    Category: Advertised Projects Constr.
    Budget Section: 1B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $7,200,000.00
    State Cost: $1,800,000.00
    Total Cost: $9,000,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/30/2024
    Project Initiation Form PIF Entered 10/30/2024
    Project Initiation Form PRC Submitted 10/30/2024
    Project Review Committee PRC Approved 11/22/2024
    Project Status Advertised 11/01/2025
    Project Management
    100% Design 100% Package Received 06/25/2025
    100% Design 100% Package Comments to DE 07/16/2025
    100% Design 100% Package Comments to DE 07/16/2025
    75% Design 75% Package Received 05/05/2025
    75% Design 75% Package Comments to DE 06/04/2025
    Final Design PS&E Received 08/01/2025
    Final Design PS&E to FAPRO 10/20/2025