Project Description: |
BOSTON- BRIDGE REPLACEMENT, B-16-199 (3H6), DORCHESTER AVENUE OVER SOUTH BOSTON BYPASS AND RUNNING TRACK
This project will replace the bridge carrying Dorchester Avenue over the South Boston Bypass and the Boston Terminal Running Track.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Robert N Rottenbucher |
Estimated Total Contract Cost: | $20,403,750.00 |
Estimated Total Federal Participating Construction Cost: | $22,014,187.50 |
District: | District 6 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|