Project Description:
BURLINGTON TO READING- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF I-95/128
This project is for the replacement of the existing guide and traffic signs on I-95 (Route 128) between US Route 3 North in Burlington and I-93 in Woburn, including applicable signing on secondary roadways.
Location:
  • Town of Burlington
  • Town of Reading
  • City of Woburn
  • Construction Begins: Winter 2025/2026
    Resident Engineer: -- not assigned --
    Construction Bid Price: $1,296,356.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 4

    Contracts (1) Progress
    # 132997 -- Construction Contract
    Guide and Traffic Sign Replacement on a Section of I-95/128

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/21/2026
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: BURLINGTON
    LEXINGTON
    READING
    WOBURN
    Category: Advertised Projects Constr.
    Budget Section: 2A
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Hwy Safety Improvement Prgm (HSIP)
    Federal Cost: $1,667,106.00
    State Cost: $185,234.00
    Total Cost: $1,852,340.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/06/2025
    Project Initiation Form PIF Entered 01/06/2025
    Project Initiation Form PRC Submitted 01/07/2025
    Project Review Committee PRC Approved 02/27/2025
    Project Status Advertised 11/15/2025
    Project Management
    100% Design 100% Package Received 06/17/2025
    100% Design 100% Package Comments to DE 07/28/2025
    75% Design 75% Package Received 06/17/2025
    Final Design PS&E Received 09/15/2025
    Final Design PS&E to FAPRO 10/30/2025
    Consultant Contract Process NTP Issued 01/24/2025