FOXBOROUGH- INSTALLATION OF OVERHEAD SIGN STRUCTURES WITH LANE USE SIGNS AT 6 LOCATIONS ON ROUTE 1 (NEAR GILLETTE STADIUM)
The purpose of the overhead gantries with lane use signs is to direct motorists traveling to and from Gillette Stadium and support use of the shoulder-lane for travel as well as use of a counter-flow lane to funnel traffic into dedicated parking areas and back to the major interstates post-event. The full matrix LED lane use signs on the gantries could allow for a lane to be designated as bus only during the event day traffic management. This will be a tangible benefit to support MSP and the traffic management for all stadium events and support public safety.
Location:
  • Town of Foxborough
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Michelle Boucher
    Estimated Total Contract Cost: $4,215,000.00
    Estimated Total Federal Participating Construction Cost: $4,727,050.00
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/06/2025
    Project Initiation Form PIF Entered 01/28/2025
    Project Initiation Form PRC Submitted 01/28/2025
    Project Review Committee PRC Approved 02/07/2025