Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOURNE- CONSTRUCTION CONTRACT FOR DEEP FOUNDATION LOAD TESTING IN ADVANCE OF SAGAMORE BRIDGE REPLACEMENT (CAPE COD BRIDGES PROGRAM)
The scope of work will involve the installation and load testing of drilled shafts, driven H-piles, driven pipe piles and drilled micro-piles. Drilled shaft testing will utilize bi-directional load cells (Osterberg Cells). Dynamic driven pile testing will use Pile Driving Analysis and Case Pile Wave Analysis Program techniques coupled with static axial compression and tension tests. Verification testing will use static tension tests for micro-piles and static lateral load testing of driven and drilled piles.
Location:
  • Town of Bourne
  • Construction Begins: Autumn 2025
    Resident Engineer: Neal Noversa
    Construction Bid Price: $5,507,294.00
    District: District 5
    Current Status: The contractor is not actively working on the project site. Proposed tree clearing operations are tentatively scheduled to start Wednesday 02/18/26. Erosion Control installation and construction of the temporary access road will follow in the Spring season. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Scheduled work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 02/17/2026)

    Contracts (1) Progress
    # 132404 -- Construction Contract
    Construction Contract for Deep Foundation Load Testing in Advance of Sagamore Bridge Replacement (Cape Cod Bridges Program) 2% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/18/2025
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/25/2025
    Project Initiation Form PIF Entered 02/25/2025
    Project Initiation Form PRC Submitted 02/25/2025
    Project Review Committee PRC Approved 03/07/2025
    Project Status Advertised 09/13/2025
    Project Management
    100% Design 100% Package Received 05/22/2025
    Final Design PS&E Received 05/22/2025
    Final Design PS&E Received - Resub 1 07/23/2025