Project Description: |
BOSTON- TUNNEL PRESERVATION, INSTALLATION, AND REPLACEMENT PUMPS AND CONTROLS ON MHS
This project will renovate or replacement pump station facilities, including roof replacement, SCADA and electrical upgrades, pump replacement, ventilation upgrades, and building repairs.
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | John Czach![]() |
Estimated Total Contract Cost: | $50,000,000.00 |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 6 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges |
|
|
|