Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
FRAMINGHAM- CHRIS WALSH MEMORIAL TRAIL (DESIGN ONLY)
The project will allow for pedestrian access to and from downtown Framingham and the public recreation areas at Farm Pond Park and Cushing Memorial Park, a new connection that will be critical to improving access, safety, and quality of life for many residents.
Location:
  • Town of Framingham
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Lawrence Cash
    Estimated Total Contract Cost: $25,740,000.00
    Estimated Total Federal Participating Construction Cost: $26,812,500.00
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 04/10/2025
    Project Initiation Form PIF Entered 04/10/2025
    Project Initiation Form PRC Submitted 04/10/2025
    Project Review Committee PRC Approved 05/28/2025
    Project Management