| Project Description: |
LEE- BRIDGE PRESERVATION, L-05-044, I-90 (EB/WB) OVER US 20 AND HOUSATONIC RIVER
This project will consist of bridge preservation at the I-90 Eastbound/Westbound bridge over US-20 and the Housatonic River, in the Town of Lee. The bridge preservation scope will include deck patching and joint repair.
|
| Location: |
|
| Design Responsibility: | In-House Boston |
| Right of Way Responsibility: | MassDOT |
| Project Manager: | Alina Daragan![]() |
| Estimated Total Contract Cost: | $2,800,000.00 |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 1 |
| Current Status: | This project is in the preliminary design phase. |
|