Project Description: |
GREENFIELD- BRIDGE REPLACEMENT, G-12-068, US 5/SR 10 (BERNARDSTON ROAD) OVER CHERRY RUM BROOK
|
Location: |
|
Design Responsibility: | Consultant |
Right of Way Responsibility: | MassDOT |
Project Manager: | Kathy Dougherty![]() |
Estimated Total Contract Cost: | $3,607,200.00 |
Estimated Total Federal Participating Construction Cost: | $3,874,400.00 |
District: | District 2 |
Current Status: | This project is in the preliminary design phase. |
|
Bridges
|
|
|
|