| Project Description:
|
BOSTON- CANTON- BRIDGE PAINTING AND MAINTENANCE OF 3 BRIDGES: B-16-272 (3F6), C-02-036 (35H, 35J)
|
| Location:
|
City of Boston
Town of Canton
|
| Design Responsibility:
|
In-House Boston |
| Right of Way Responsibility:
|
MassDOT |
| Construction Begins:
|
Autumn 2026 |
| Project Manager:
|
Alina Daragan |
| Estimated Total Contract Cost:
|
$8,434,431.50 |
| Estimated Total Federal Participating Construction Cost:
|
N/A |
| District:
|
District 6 |
| Current Status:
|
This project has been advertised for construction bids. (as of 06/06/2026 ) |