BOSTON- SCHEDULED AND EMERGENCY WATER QUALITY CONTROL STRUCTURES (WQCS) CLEAN OUT & REPAIR IN I-90 & I-93 TUNNELS
District will undertake cleaning and repair of water quality control structures.
Location:
  • City of Boston
  • Construction Begins: Summer 2026
    Resident Engineer: John Perampalam
    Construction Bid Price: $645,024.85
    District: District 6

    Contracts (1) Progress
    # 134292 -- Construction Contract
    Scheduled and Emergency Water Quality Control Structures (WQCS) Clean Out & Repair in I-90 & I-93 Tunnels

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/23/2026
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/16/2025
    Project Initiation Form PIF Entered 05/16/2025
    Project Initiation Form PRC Submitted 05/16/2025
    Project Review Committee PRC Approved 05/19/2025
    Project Status Advertised 05/02/2026
    Project Management
    100% Design 100% Package Received 04/16/2026
    Final Design PS&E Received 04/22/2026
    Final Design PS&E to FAPRO 04/27/2026