Project Description:
DISTRICT 5- SCHEDULED AND EMERGENCY PAVEMENT REPAIRS AT VARIOUS LOCATIONS (AREAS A, B & C)
This project consists of maintenance resurfacing and roadway repairs at various locations throughout District 5 in Areas A, B and C. The work to be done includes pavement milling and/or the placement of Superpave hot mix asphalt, or a combination of these items as directed on various State-owned roadways. Other work to be done includes installing new ADA compliant wheelchair ramps, adjusting and rebuilding drainage, sanitary, and water structures, removing and resetting drainage structure frame and grates or covers, removing and resetting granite curbs, installing rumble strips at shoulders on high volume, multilane roadways, installing wire loops as required, installing new pavement markings, erosion controls, and other miscellaneous work.
Location:
  • City of Attleboro
  • Town of Mattapoisett
  • Town of Norton
  • Town of Norwood
  • City of Taunton
  • Construction Begins: Spring 2026
    Resident Engineer: Sean Darling
    Construction Bid Price: $13,759,992.25
    District: District 5
    Current Status: Upcoming Milling, Drainage Structure, and Paving operations at various, small and large priority locations all over Areas A, B, & C, as well as at four very large locations: Attleboro sections of Rte. 1A b/w Rhode Island SL and Rte. 1; Mattapoisett sections of Rte. 6 b/w Church St. and Mattapoisett/Fairhaven TL; Norwood sections of Rte. 1 b/w Coney St. and Norwood/Westwood TL; Taunton/Norton sections of Rte. 140 b/w Chapel Street and Norton Center. Scheduled work hours are Sunday through Friday, 8:00 PM to 5:00 AM. Expect periodic lane closures and restrictions. (as of 08/14/2026)

    Contracts (1) Progress
    # 133576 -- Construction Contract
    Scheduled and Emergency Pavement Repairs at Various Locations (Areas A, B & C) 7% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/22/2026
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/29/2025
    Project Initiation Form PIF Entered 05/29/2025
    Project Initiation Form PRC Submitted 06/07/2025
    Project Review Committee PRC Approved 06/09/2025
    Project Status Advertised 02/07/2026
    Project Management
    100% Design 100% Package Received 01/27/2026
    Final Design PS&E Received 01/30/2026
    Final Design PS&E to FAPRO 01/30/2026