Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 5- SCHEDULED AND EMERGENCY SUBSTRUCTURE REPAIRS AT VARIOUS LOCATIONS
The work under this project shall consists of scheduled an emergency substructure repairs 1) Removing the deteriorated concrete from any element of the substructure, including but not limited to stem piers, pier caps, pier columns, wing walls, backwalls, and abutments. 2) Jacking and shoring to support pier caps and/or various beams over piers and abutments may be required to allow concrete repairs to the substructure. 3) Removing the deteriorated concrete from retaining walls, both connected/associated and not connected/not associated with any bridge in the jurisdiction of District 5. 4) Replacing excavated, spalled, delaminated, or deteriorated concrete, and replacing any broken, missing or deteriorated reinforcing steel with new material. 5) Removing and resetting or replacing bearing devices as required. 6) Replacing missing or damaged granite or cement concrete slope paving, either in kind or with cement concrete slope paving where needed and as directed by the Engineer. 7) Any additional repairs in either the superstructure or deck that are related to the substructure work.
Location:
Construction Begins: Winter 2025/2026
Resident Engineer: Michael Horton
Construction Bid Price: $3,437,725.00
District: District 5
Current Status: - MIG has work staged at a few work order locations: WO #1 & 2: Rt-18 under Rt-6, New Bedford WO #3: I-195 under Anthony Street Seekonk Crew is continuing concrete substructure repairs at each location Normal work hours are Monday through Friday, 9:00 PM to 5:30 AM. Expect periodic lane closures and restrictions. (as of 06/03/2026)
Additional Info: WO#3 location has completed all concrete repairs. Concrete protective coating application to be scheduled after full curing. (as of 06/03/2026)

Contracts (1) Progress
# 132949 -- Construction Contract
Scheduled and Emergency Substructure Repairs at Various Locations 16% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/26/2025
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/29/2025
    Project Initiation Form PIF Entered 05/29/2025
    Project Initiation Form PRC Submitted 05/30/2025
    Project Review Committee PRC Approved 06/02/2025
    Project Status Advertised 11/08/2025
    Project Management
    100% Design 100% Package Received 07/25/2025
    100% Design 100% Package Comments to DE 08/14/2025
    Final Design PS&E Received 08/27/2025
    Final Design PS&E to FAPRO 11/03/2025