Project Description:
DISTRICT 5- SCHEDULED AND EMERGENCY STEEL AND CONCRETE BEAM REPAIRS AT VARIOUS LOCATIONS
The scope of work under this contract is to perform scheduled and emergency steel and concrete beam repairs on bridges throughout District Five. The work consists of furnishing all necessary labor, materials and equipment required to perform related work incidental to a project of this nature.
Location:
Construction Begins: Winter 2025/2026
Resident Engineer: Michael Horton
Construction Bid Price: $2,186,650.00
District: District 5
Current Status: NEL Corporation completed work at Work Order #1 – I-195 under Shawmut Ave (New Bedford) - Timber Blocking was required w/ steel repair designs to follow WO#2 has been issued to NEL in Kingston Normal work hours are Monday through Friday, 9:00 PM to 5:30 AM Expect periodic lane closures and restrictions. (as of 04/22/2026)

Contracts (1) Progress
# 133235 -- Construction Contract
Scheduled and Emergency Steel and Concrete Beam Repairs at Various Locations 2% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/13/2026
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    NEL Corporation completed work at Work Order #1 – I-195 under Shawmut Ave (New Bedford) - Timber Blocking was required w/ steel repair designs to follow WO#2 has been issued to NEL in Kingston Normal work hours are Monday through Friday, 9:00 PM to 5:30 AM Expect periodic lane closures and restrictions.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/29/2025
    Project Initiation Form PIF Entered 05/29/2025
    Project Initiation Form PRC Submitted 05/30/2025
    Project Review Committee PRC Approved 06/02/2025
    Project Status Advertised 12/20/2025
    Project Management
    100% Design 100% Package Received 10/16/2025
    100% Design 100% Package Comments to DE 11/05/2025
    75% Design 75% Package Received 08/21/2025
    75% Design 75% Package Comments to DE 09/30/2025
    Final Design PS&E Received 11/18/2025
    Final Design PS&E to FAPRO 12/12/2025