SOMERSET- BRIDGE PAINTING AND PRESERVATION, S-16-009, BRAYTON POINT ROAD OVER I-195
The scope of work under this contract is to perform routine maintenance activities at the bridge carrying Brayton Point Road over I-195 in Somerset. The work consists of furnishing all necessary labor, materials and equipment required to perform the work described in the contract documents, as well as all other related work incidental to a project of this nature.
Location:
  • Town of Somerset
  • Construction Begins: Spring 2026
    Resident Engineer: Nelson Borges
    Construction Bid Price: $1,887,764.24
    District: District 5

    Contracts (1) Progress
    # 133791 -- Construction Contract
    Bridge Painting and Preservation, S-16-009, Brayton Point Road over I-195

    Bridges

    Contract Dates
    Notice to Proceed: 05/15/2026
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/29/2025
    Project Initiation Form PIF Entered 05/29/2025
    Project Initiation Form PRC Submitted 05/30/2025
    Project Review Committee PRC Approved 06/02/2025
    Project Status Advertised 03/07/2026
    Project Management
    100% Design 100% Package Received 12/22/2025
    100% Design 100% Package Comments to DE 01/20/2026
    75% Design 75% Package Received 11/07/2025
    75% Design 75% Package Comments to DE 12/09/2025
    Final Design PS&E Received 02/18/2026
    Final Design PS&E to FAPRO 03/02/2026