Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
FALL RIVER- BRIDGE PRESERVATION, F-02-065, FOURTH STREET OVER I-195
The scope of work under this contract is to perform routine maintenance activities at the bridge carrying Fourth Street over I-195 in Fall River. The work consists of furnishing all necessary labor, materials and equipment required to perform the work described in the contract documents, as well as all other related work incidental to a project of this nature.
Location:
  • City of Fall River
  • Design Responsibility: In-House Boston
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2026
    Project Manager: Albin Napit
    Estimated Total Contract Cost: $2,000,000.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/29/2025
    Project Initiation Form PIF Entered 05/29/2025
    Project Initiation Form PRC Submitted 05/30/2025
    Project Review Committee PRC Approved 06/02/2025
    Project Management