Project Description:
DISTRICT 5- SCHEDULED AND EMERGENCY TRAFFIC SIGNAL REPAIRS AND IMPROVEMENTS AT VARIOUS LOCATIONS
The work under this contract consists of supplying, constructing, and installing traffic signal related items at various signalized locations as directed by the Engineer. Ancillary items of work such as wheelchair ramp construction, curb resetting, sidewalk replacement, pavement patching and resurfacing may also be included.
Location:
Construction Begins: Spring 2026
Resident Engineer: Shawn Morris
Construction Bid Price: $1,448,378.00
District: District 5

Contracts (1) Progress
# 133482 -- Construction Contract
Scheduled And Emergency Traffic Signal Repairs and Improvements at Various Locations

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/30/2026
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/30/2025
    Project Initiation Form PIF Entered 05/30/2025
    Project Initiation Form PRC Submitted 06/10/2025
    Project Review Committee PRC Approved 06/16/2025
    Project Status Advertised 01/24/2026
    Project Management
    100% Design 100% Package Received 12/08/2025
    75% Design 75% Package Received 12/08/2025
    Final Design PS&E Received 12/15/2025
    Final Design PS&E to FAPRO 01/16/2026