DISTRICT 5- HIGHWAY DELINEATOR REPLACEMENT AND RELATED WORK AT VARIOUS LOCATIONS
The work under this contract consists of furnishing all necessary labor, materials, and equipment required to perform the work described below, as well as all other related work incidental to a project of this nature. Work includes installing both soil anchor and surface mounted type flexible delineator posts at various locations in District 5 as directed by the Engineer.
Location:
Construction Begins: Winter 2025/2026
Resident Engineer: Duarte DaSilva
Construction Bid Price: $487,761.00
District: District 5

Contracts (1) Progress
# 132994 -- Construction Contract
Highway Delineator Replacement and Related Work at Various Locations 20% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/14/2026
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 05/30/2025
    Project Initiation Form PIF Entered 05/30/2025
    Project Initiation Form PRC Submitted 06/10/2025
    Project Review Committee PRC Approved 06/16/2025
    Project Status Advertised 11/15/2025
    Project Management
    100% Design 100% Package Received 10/24/2025
    Final Design PS&E Received 10/31/2025
    Final Design PS&E to FAPRO 11/04/2025