Project Description:
DISTRICT 3- SCHEDULED AND EMERGENCY BRIDGE DECK AND JOINT REPAIRS AT VARIOUS LOCATIONS
This project consists of scheduled and emergency deck and joint repairs at various location throughout the district as needed and directed by the Engineer.
Location:
Construction Begins: Summer 2026
Resident Engineer: Marghrit Arous
Construction Bid Price: $2,509,550.00
District: District 3

Contracts (1) Progress
# 134288 -- Construction Contract
Scheduled and Emergency Bridge Deck and Joint Repairs at Various Locations

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/07/2026
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/07/2025
    Project Initiation Form PIF Entered 07/05/2025
    Project Initiation Form PRC Submitted 07/05/2025
    Project Review Committee PRC Approved 07/07/2025
    Project Status Advertised 05/02/2026
    Project Management
    100% Design 100% Package Received 03/31/2026
    75% Design 75% Package Received 02/10/2026
    75% Design 75% Package Comments to DE 03/11/2026
    Final Design PS&E Received 04/17/2026
    Final Design PS&E to FAPRO 04/27/2026