Project Description:
DISTRICT 3- SCHEDULED AND EMERGENCY STRUCTURAL AND SUBSTRUCTURE AND RELATED REPAIRS AT VARIOUS LOCATIONS
The work under this contract shall include scheduled and emergency substructure and structural repairs at various locations throughout the district, as needed and as directed by the Engineer.
Location:
Design Responsibility: In-House Boston
Right of Way Responsibility: MassDOT
Construction Begins: Winter 2026/2027
Project Manager: Genesis PozDiaz
Estimated Total Contract Cost: $2,529,000.00
Estimated Total Federal Participating Construction Cost: N/A
District: District 3
Current Status: This project has been advertised for construction bids. (as of 10/10/2026 )

Contracts (0) Progress
No contracts associated with this project

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/07/2025
    Project Initiation Form PIF Entered 07/05/2025
    Project Initiation Form PRC Submitted 07/05/2025
    Project Review Committee PRC Approved 07/07/2025
    Project Status Advertised 10/10/2026
    Project Management
    75% Design 75% Package Received 05/29/2026
    75% Design 75% Package Comments to DE 06/29/2026
    Final Design PS&E Received 07/24/2026
    Final Design PS&E Received - Resub 1 08/20/2026