DISTRICT 3- BRIDGE DRAINAGE CLEANING AND RELATED WORK AT VARIOUS LOCATIONS
The work under this contract shall consist of bridge drainage cleaning and repairs throughout the district as needed and directed by the Engineer.
Location:
Construction Begins: Winter 2025/2026
Resident Engineer: Grant Maffei
Construction Bid Price: $1,022,142.00
District: District 3

Contracts (1) Progress
# 133272 -- Construction Contract
Bridge Drainage Cleaning and Related Work at Various Locations 42% Complete

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/19/2026
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/07/2025
    Project Initiation Form PIF Entered 07/05/2025
    Project Initiation Form PRC Submitted 07/05/2025
    Project Review Committee PRC Approved 07/07/2025
    Project Status Advertised 12/27/2025
    Project Management
    100% Design 100% Package Received 11/12/2025
    100% Design 100% Package Comments to DE 12/01/2025
    75% Design 75% Package Received 09/23/2025
    75% Design 75% Package Comments to DE 10/24/2025
    Final Design PS&E Received 12/03/2025
    Final Design PS&E to FAPRO 12/19/2025