Project Description:
DISTRICT 4- SCHEDULED & EMERGENCY DRAINAGE REPAIRS AND IMPROVEMENTS AT VARIOUS LOCATIONS
District 4 Scheduled & Emergency Drainage Repairs and Improvements at Various Locations
Location:
Design Responsibility: In-House Boston
Right of Way Responsibility: MassDOT
Construction Begins: Autumn 2026
Project Manager: Andre Breneville
Estimated Total Contract Cost: $1,000,000.00
Estimated Total Federal Participating Construction Cost: N/A
District: District 4
Current Status: Final Package to FAPRO (as of 06/12/2026 )

Contracts (0) Progress
No contracts associated with this project

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 06/24/2025
    Project Initiation Form PIF Entered 06/24/2025
    Project Initiation Form PRC Submitted 06/24/2025
    Project Review Committee PRC Approved 06/30/2025
    Project Management
    100% Design 100% Package Received 06/04/2026
    Final Design PS&E Received 06/10/2026
    Final Design PS&E to FAPRO 06/12/2026