Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 4- VRU MISSING CROSSWALKS AT STATE SIGNALS AT MULTIPLE LOCATIONS
Location:
Design Responsibility: Consultant
Right of Way Responsibility: MassDOT
Construction Begins: Autumn 2026
Project Manager: Jonathan E Freeman
Estimated Total Contract Cost: $1,124,714.00
Estimated Total Federal Participating Construction Cost: $1,268,642.50
District: District 4
Current Status: 75% Package Comments to DE (as of 01/08/2026 )

Contracts (0) Progress
No contracts associated with this project

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/25/2025
    Project Initiation Form PIF Entered 08/25/2025
    Project Initiation Form PRC Submitted 08/26/2025
    Project Review Committee PRC Approved 09/24/2025
    Project Management
    25% Design 25% Package Received 12/08/2025
    75% Design 75% Package Received 12/08/2025
    75% Design 75% Package Comments to DE 01/08/2026