Project Description:
DISTRICT 5- VRU MISSING CROSSWALKS AT STATE SIGNALS AT MULTIPLE LOCATIONS
Bus stops were screened by HQ Safety to identify Vulnerable Road Users (VRU) bus stops at State signals. A MassDOT manual desktop review identified signals with missing crosswalks as candidates. These candidates were shared with Districts and Regional Transit Authorities (RTA) for input. Traffic movement counts (TMCs) were conducted in June, before school ended. Howard Stein Hudson completed conceptual sketches and reviewed operational analysis for the top 20 locations throughout the State. This project will be a multi-year effort with this being the first year. In order to allow for a streamlined process and expedited project delivery, FY26 are candidates where no/minimal Right of Way (ROW) is included in the design, the scope of work requires less reconstruction, and minimal outreach/coordination is required to advance design. Improvements will include some or all of the following: changes to traffic signal timing, phasing, coordination, detection, addition or reconstruction of curb ramps and crosswalks, providing Accessible Pedestrian Signals (APS) push buttons with countdown pedestrian signal heads, reconstruction of sidewalks connecting signalized intersections with bus stops, restricting right turns on red, and minor geometric changes. This project involves upgrades at 2 locations for VRUs at or near MassDOT owned signals near bus stops in District 5. The first location is located in Falmouth, at the intersection of North Falmouth Hwy (Route 28A) at County Rd/Nathan Ellis Hwy (Route 151). The second location is located in North Attleborough, at the intersection of South Washington St (Route 1) at Emerald Square Mall North Driveway.
Location:
Design Responsibility: Consultant
Right of Way Responsibility: MassDOT
Project Manager: Jonathan E Freeman
Estimated Total Contract Cost: $1,056,079.25
Estimated Total Federal Participating Construction Cost: $1,186,623.75
District: District 5
Current Status: 75% Package Comments to DE (as of 01/08/2026 )

Contracts (0) Progress
No contracts associated with this project

Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 08/25/2025
    Project Initiation Form PIF Entered 08/25/2025
    Project Initiation Form PRC Submitted 08/26/2025
    Project Review Committee PRC Approved 09/24/2025
    Project Management
    25% Design 25% Package Received 12/08/2025
    75% Design 75% Package Received 12/08/2025
    75% Design 75% Package Comments to DE 01/07/2026
    75% Design 75% Package Comments to DE 01/08/2026