Project Description:
HOLLISTON- IMPROVEMENTS AT THE INTERSECTION OF ROUTE 16 (WASHINGTON STREET) AND WHITNEY STREET AND APPROACHES (DESIGN ONLY)
The Town of Holliston seeks to improve the safety, functionality, and aesthetic quality of Route 16 (Washington St.) between Locust St. and the Sherborn Town Line and will focus on the Whitney St.intersection, along with the intersections of the Holliston Rail Trail crossing and the Covanta Waste Commercial entrance. The project will address multiple challenges including congestion,pedestrian and cyclist safety, intersection and stormwater management deficiencies. The project will also improve safety by providing adequate facilities on Route 16 - Washington Street to keep commercial traffic off of local residential roads.
Location:
  • Town of Holliston
  • Design Responsibility: Municipality
    Right of Way Responsibility: Municipality
    Project Manager: Alolade O Campbell
    Estimated Total Contract Cost: $14,224,500.00
    Estimated Total Federal Participating Construction Cost: $14,550,000.00
    Funding Provision: This project is planned to be funded through the 2026 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 3
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2026
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: HOLLISTON
    Category: Design and Force Agreements
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • added for design activity only
  • Category FA - Ntl. Hwy Perform. Prgm (NHPP) - NHS
    Federal Cost: $280,000.00
    State Cost: $70,000.00
    Total Cost: $350,000.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/11/2025
    Project Initiation Form PIF Entered 09/11/2025
    Project Initiation Form PRC Submitted 09/11/2025
    Project Review Committee PRC Approved 09/24/2025
    Project Management